ActivityDepends onNext ActivityTime requirementEarly StartEarly FinishLate StartLate FinishFree FloatTotal Float
ad1012302
be, f2020200
cg3032502
dah4153722
ebh5272700
fbj42691377
gci63951102
hd, ej671371300
igj2911111322
jf, h, i31316131600

Activity Details

Activity Name

Time

Dependency

a

b

c

d

e

f

g

h

i

j

PathTime
a, d, h, j14
b, e, h, j16
b, f, j9
c, g, i, j14
Critical PathTime
b, e, h, j16

Critical Path Method

Total Float

Total Float = Late start date – Early start date

Total Float = Late Finish date – Early Finish date

Free Float

Free Float = ES of next Activity – EF of Current Activity